Large Load Queue Has Tripled in Texas: Grid Roundup #76
Biggest coal plant in Texas offline for two years; peak demand is down, energy use is up in Texas; forward prices for 2026-2030 are up 15-20%; 70% of Texas' large load queue is data centers
In this issue:
State’s largest and newest coal plant is offline for two years
Peak demand for August was down, minimum demand was up
Forward prices are up 15-20% compared to last year
Large load queue has tripled in the last year and is now 70% data centers; hydrogen is almost completely gone
I’ll host a subscriber chat next week Monday, September 22 from 3:00 - 4:00 during the ERCOT Board meeting. The chat, Grid Roundups including the one below, weekly Reading & Podcast Picks, the full archives and special episodes of the Energy Capital Podcast including this one with … are available for paid subscribers only. Please become one today.
Keep reading with a 7-day free trial
Subscribe to The Texas Energy and Power Newsletter to keep reading this post and get 7 days of free access to the full post archives.